Hi MM Expert,
We've some problem with warehouse officer that's problem related to SAP-PM. I don't know reason why they do not purchas material base-on reorder point and keep stock level in safety stock? or all they STUPID? Never think to provent material shortage that's impact for maintenance order. Who are SAP-MM expert? Please expain method of material management. Panuphan B. Maintenance Information Manager PTT Aromatics and Refining Public Company Limited |
|||
|
Before frustrated, better talk to them and investigate why. When I was SAP PM, my scope keeps on expanding to include SAP MM and Accunting to make SAP PM fully working. So take the leadership!
I would like to know whether the reorder point is set in the first place. Do maintenance guys register all their spares, defines whether they are stock with their min/max levels, non-stock, capm, etc and update their equipment bills of materials. How do you manage material return to warehouse if not used? How do you do material cataloging? These questions should be answered by maintenance guys first, I guess. This message has been edited. Last edited by: Josh, |
||||
|
I am no MM expert but wish to make comments.
Are requisitions being automatically created when the material quantity drops below the re-order point? If your SAP Material masters are properly configured then there is little need for the warehouse officer to think. Reservations can also made to PM Orders and if they are properly scheduled in SAP then you can ensure that all parts are available when needed. You can even make it so that purchase orders are automatically generated and sent to the vendor. All your Warehouse officer needs to do is receipt the goods when they arrive. |
||||
|
Josh, I've to talk with them many time long and long time ago and share knowledge with them. But they do not never and never listen maintenance planning. Our organization separate Warehouse Division from Maintenance, thier objective focusing how to minimum inventory cost use method by feeling. However, they saided, run MRP everyweek but materials still are shortage? or the problem is bad maintenance strategy? Panuphan B. Maintenance Information Manager PTT Aromatics and Refining Public Company Limited |
||||
|
David, they used MRP for dicision to buy material but manually not automatically. They have to told me in the meeting something like that and they also saided SAP-MM do not provide. !@!@#!# I don't believe that. ##@$@#$ Panuphan B. Maintenance Information Manager PTT Aromatics and Refining Public Company Limited |
||||
|
What sort of material shortages did you face? Pls give examples before we can comment further. Maybe those materials are not considered stock items so no stocks available in warehouse.
|
||||
|
Material for critical pump (condensate feed pump)e.g. o-ring mech. seal... etc. I don't why they get these material shortage and some material will go to Singapore.
Panuphan B. Maintenance Information Manager PTT Aromatics and Refining Public Company Limited |
||||
|
O ring & mech seal are stock items so these should be procured upon withdrawal but does your company have a price agreement ready to avoid the long purchasing process for this kind of items?
|
||||
|
Usually, It have distributor and supplier in Thailand. But some part its need to order oversea and do not stock in there suplier warehouse. Now a day, we have spare consignment with suplier only consumed part.
Panuphan B. Maintenance Information Manager PTT Aromatics and Refining Public Company Limited |
||||
|
The best approach is using MRP type PD on the material master with safety stock. This way all reservations on orders with a date in the future are taken into account resulting in more of a "just in time" approach for MRO spares. This in conjunction with other settings and some user exit coding for receipts of MRO material and automatically create req's/PO's and then on the receipt side, combining a "PO receipe" with a "goods issue to a work order (when a reservation exists)" are means of automating the entire process.
Ben Mansi Vesta Partners, LLC |
||||
|
Thank you all, I've appointment from Warehouse officer and we will talk together and develop "Stock Policy", they saided.
But I'm not sure what is scope of Stock policy.... Panuphan B. Maintenance Information Manager PTT Aromatics and Refining Public Company Limited |
||||
|
Have you sorted your problem yet? I am visiting Thailand in April. My company has considerable experience of MRO inventory issues in the Oil, Gas, and Petroleum Industries. If you would like to contact me please reply via this forum.
Kind regards |
||||
|
Now, we have setting stock policy and implementing MRO process for our objective....but some point of process not clear and not understand for all member....I know someone in their warehouse division didn't more experience......
my question in their meeting....why don't use ROP for calculated....They answer me that the ROP concept could not use for our business....I'm stop my next question and feeling bad. Panuphan B. Maintenance Information Manager PTT Aromatics and Refining Public Company Limited |
||||
|
Can you answer a few questions please:
1) Do you have a written maintenance strategy? 2) Do you have a written repair strategy? 3) Do you have an up to date criticality study? 4) Do you use Bills of Materials (BOMs)? 5) Do you have a written spares strategy? 6) How many of these strategies are referred to when setting stock levels? If you are having trouble setting ROP levels we can help. Kind regards |
||||
|
Most of these question are in place and during review and implementing e.g. spares strategy. But some of these I'm not sure it is effectiveness or not especially spare strategy.
Panuphan B. Maintenance Information Manager PTT Aromatics and Refining Public Company Limited |
||||
|