Converting PO plans with PO positions to a PO strategy plan in SAP PM|
Go
![]() |
New
![]() |
Find
![]() |
Notify
![]() |
Tools
![]() |
Reply
![]() |
|
In my plant I'm dealing with the fact that I've multiple PO plans with numerous so-called PO positions. These individual PO plans all have their own frequency.
I would like to perform a batch operation in order to get one or two PO plans with a whole lot of different PO positions attached to it. They all have to have their own frequency. Is there a fast and accurate way of converting the existing PO plans to a so-called strategy plan and get all the frequencies right for all of the different PO positions? I hope to read your replies soon. With regards, With regards, Robert Somers M.Sc. |
|||
|
PO = ?
|
||||
|
uhm..
it's a dutch abbreviation. I meant PM plan and PM position and PM strategy plan. I hope you all understand my question now. regards Robert With regards, Robert Somers M.Sc. |
||||
|
By PO positions, do you mean the points where the PM will be triggered?
If you want to combine several PMs with different frequencies, you have to set up your maintenance strategy right first, don't you? |
||||
|
| Previous Topic | Next Topic | powered by eve community |
| Please Wait. Your request is being processed... |
|
Join or Manage Your Profile
Posting Boards
Enterprise Asset Management EAM & Computerized Maintenance Management Systems CMMS
Posts About SAP®-EAM (PM Plant Maintenance)
Converting PO plans with PO positions to a PO strategy plan in SAP PM