In my plant I'm dealing with the fact that I've multiple PO plans with numerous so-called PO positions. These individual PO plans all have their own frequency.
I would like to perform a batch operation in order to get one or two PO plans with a whole lot of different PO positions attached to it. They all have to have their own frequency.
Is there a fast and accurate way of converting the existing PO plans to a so-called strategy plan and get all the frequencies right for all of the different PO positions?
I hope to read your replies soon.

With regards,


With regards,

Robert Somers M.Sc.
 
Posts: 2 | Location: Haarlem | Registered: 05 January 2008Reply With QuoteEdit or Delete MessageReport This Post
Posted Hide Post
PO = ?
 
Posts: 124 | Location: Melbourne, Australia | Registered: 05 May 2004Reply With QuoteEdit or Delete MessageReport This Post
Posted Hide Post
uhm..

it's a dutch abbreviation. I meant PM plan and PM position and PM strategy plan.

I hope you all understand my question now.

regards Robert


With regards,

Robert Somers M.Sc.
 
Posts: 2 | Location: Haarlem | Registered: 05 January 2008Reply With QuoteEdit or Delete MessageReport This Post
Posted Hide Post
By PO positions, do you mean the points where the PM will be triggered?

If you want to combine several PMs with different frequencies, you have to set up your maintenance strategy right first, don't you?
 