Hi Everybody
I am involve in the data entry of Floating Production, Storage and Offloading (FPSO) for offshore oil and gas E&P. We used P&ID drawings to cover all the assets- main equipment, valves and instruments, that are installed onboard. Then it will be uploaded to Maximo which will be used for the maintenance program. We have thousands of valves and instruments found on these drawings and I would like to know if these will have the same number of work orders that will be generated? ALso, up to what extent are valves and instruments included in the PM and PdM program? Thanks in advance. Albert |
|||
|
How a cutoff point of 50mm dia.?
|
||||
|
We are also in implementation stage of Maximo. What we have done in the beginning is excluding the minor motors, pumps, valves of package units. For example, a small plant that produces nitrogen or air etc.
|
||||
|
i think you should register all the tag first then follow your maintenance strategy for the pm
|
||||
|
| Previous Topic | Next Topic | powered by eve community |
| Please Wait. Your request is being processed... |
|
Join or Manage Your Profile
Posting Boards
Enterprise Asset Management EAM & Computerized Maintenance Management Systems CMMS
Posts About MRO by IBM (Maximo®) CMMS
PM and Pdm for Valves and Instruments